First Phase to Contain Nuke Reactor Complete

First Phase to Contain Nuke Reactor Complete

State minister in charge of handling the nuclear accident, Goshi Hosono. (File photo)

State minister in charge of handling the nuclear accident, Goshi Hosono, said that the first phase to bring the crippled Fukushima Dai-ichi nuclear power plant under control was completed as scheduled on Sunday.

Hosono said, “We believe Step 1 of stably cooling (the reactors) and eliminating risks of a hydrogen explosion has been achieved.”

According to a time schedule released by Tokyo Electric Power Co. April 17, the first phase was to take three months. The plan to end the radiation leak was split into three phases, spanning 10 years.

 

Author

Dustin Dye

Dustin Dye is the author of the YAKUZA DYNASTY series, available through the Amazon Kindle.

He lived in Okayama, Japan, where he taught English at a junior high school through the Japan Exchange and Teaching Program for three years. He is a graduate from the University of Kansas, where he received a bachelor's degree in anthropology.

His interest in Japan began in elementary school after seeing Godzilla fight Ghidorah, the three-headed monster. But it wasn't until he discovered Akira Kurosawa's films through their spaghetti Western remakes that he truly became fascinated in the people and culture of Japan.

He lives in Kansas with his wife, daughter and guinea pig.

Visit him online at www.dustindye.net.
E-mail him: [email protected]